Benchmark engagements are now open for select completed construction disputes.Learn more

A site compound of stacked temporary offices and welfare cabins.

teloform for prolongation cost

Prolongation is proved
in the period of delay.

Time-related cost is assessed by reference to the period in which the delaying event occurred, not the period at the end of the job. That single principle disposes of a large share of these claims.

The period, and the nature of the cost.

The SCL Protocol is explicit that compensation for prolongation is assessed by reference to the period when the effect of the employer risk event was felt, not by taking the rate of expenditure in the extended period at the end of the project.

The distinction matters because site establishment at the end of a job is usually lighter than during the peak. Claiming the extended period inflates the claim and is straightforward to attack.

The cost has to be genuinely time-related: site staff, accommodation, welfare, standing plant, utilities, insurances running with time. Cost caused by the event rather than by its duration belongs in a different head.

Head office overhead is a separate argument again, and formula recovery is a fallback rather than a starting point.

How prolongation is built.

From resourced records, not from a rate multiplied by a number of weeks.

01

Fix the delay periods

Establish when each compensable event actually affected progress.

02

Identify time-related cost

Separate cost that runs with time from cost caused by the event itself.

03

Resource the period

Establish actual site establishment during the delay period from the records.

04

Exclude non-compensable periods

Remove periods of contractor delay and, on the usual approach, concurrent periods.

05

Address head office overhead

Prove actual under-recovery where possible before reaching for a formula.

What the argument is built from.

Prolongation is an accounting exercise anchored to a schedule finding.

Resourced site establishment records by period
Payroll and staff allocation for site-based personnel
Plant hire and standing records with on and off dates
Accommodation, welfare, and utilities invoices
The delay analysis fixing the compensable periods
Tender allowances for preliminaries, for comparison

Where these claims fail.

The most common error is structural rather than evidential.

The extended period is used

Costing the weeks at the end of the job rather than the period of the delay overstates the claim and is easy to defeat.

Cost is not time-related

Event-caused cost claimed as prolongation duplicates other heads.

The formula is the starting point

Hudson, Emden, or Eichleay applied without first attempting actual cost invites a challenge to the whole head.

Concurrent periods are included

Where the extension arises in a concurrent period, prolongation cost generally does not follow it.

What the Matter Model does with it.

It builds the time-related cost case from resourced site records rather than from a formula, and ties each claimed cost to the delay period said to have caused it.

Every claimed day is traceable to the schedule finding that supports it, so a change in the delay analysis moves the damages with it.

Standards and authorities

  • SCL Delay and Disruption Protocol, 2nd edition (February 2017), Core Principles on prolongation
  • Eichleay Corporation, ASBCA No. 5183 (1960), on head office overhead

General reference on how these disputes are argued. Not legal advice, and not a statement of the law of every jurisdiction or seat.

Test it on a matter you already know.

Start with one completed matter.